To see the latest news on the new pipeline being installed – please take a look at the South East Water website link: Boosting resilience in Wealden | South East Water this page will also show details of upcoming works:
Location | Anticipated date |
---|---|
Newbury Lane (Road Closure) | Completed |
Monks Lane (Road Closure) | Completed |
Woods Green (Road Closure) | Mid-June 2024 to early July 2024 |
Wyck Lane (Road Crossing / Private Road) | Early July 2024 to early July |
Buckland Hill (Road Crossing) | Early July 2024 to early July 2024 |
Bewlbridge Lane (Road Crossing) | Late July 2024 to late July 2024 |
Whitegates Lane (Road Closure) | Early July 2024 to late July 2024 |
Three Oaks Lane (Road Closure) | Late July 2024 to late August 2024 |
The Slade/Cousley Wood Road (Road Crossing) | Mid-July 2024 to mid-July 2024 |
Old Station Road (Road Closure) | Late July 2024 to late August 2024 |
Three Oaks Lane (Road Crossing) | Late July 2024 to late August 2024 |
Tapsells Lane (Road Closure) | Late August 2024 to mid-September 2024 |
Sleepers Stile Road (Road Crossing) | Early August 2024 to mid-August 2024* |
Lower Cousley Wood Road (Road Crossing) | Early August 2024 to mid-August 2024* |
Station Road (Road Crossing) | Late September 2024 to early October September 2024 |
Newbury Lane (Road Crossing) | Early October 2024 to early October 2024 |