South East Water – new pipeline – details of road closures

To see the latest news on the new pipeline being installed – please take a look at the South East Water website link: Boosting resilience in Wealden | South East Water this page will also show details of upcoming works:

Location Anticipated date
Newbury Lane (Road Closure) Completed
Monks Lane (Road Closure) Completed
Woods Green (Road Closure) Mid-June 2024 to early July 2024
Wyck Lane (Road Crossing / Private Road) Early July 2024 to early July
Buckland Hill (Road Crossing) Early July 2024 to early July 2024
Bewlbridge Lane (Road Crossing) Late July 2024 to late July 2024
Whitegates Lane (Road Closure) Early July 2024 to late July 2024
Three Oaks Lane (Road Closure) Late July 2024 to late August 2024
The Slade/Cousley Wood Road (Road Crossing) Mid-July 2024 to mid-July 2024
Old Station Road (Road Closure) Late July 2024 to late August 2024
Three Oaks Lane (Road Crossing) Late July 2024 to late August 2024
Tapsells Lane (Road Closure) Late August 2024 to mid-September 2024
Sleepers Stile Road (Road Crossing) Early August 2024 to mid-August 2024*
Lower Cousley Wood Road (Road Crossing) Early August 2024 to mid-August 2024*
Station Road (Road Crossing) Late September 2024 to early October September 2024
Newbury Lane (Road Crossing) Early October 2024 to early October 2024
Location Anticipated date
Sheriff’s Lane (Road Closure) Completed
Yew Tree Lane (HDD Monitoring Only) Early July 2024 to mid-July 2024
Lake Street (Road Closure) Completed
Tonbridge Wells Road (HDD Monitoring Only) Late June 2024 to early July 2024
Rotherhurst Lane (Road Crossing) Early Mid-July 2024 to mid-July 2024*
High Cross (Road Crossing) Early August 2024 to early August 2024*
Sheriff’s Lane (Road Crossing) Completed
Wadhurst Road (Road Closure) Late July 2024 to early September 2024
Best Beech Hill (Road Closure) Early October 2024 to early March 2025
Mayfield Lane (Road Closure) Late January 2025 to mid-February 2025

*subject to Highways approval